Tower 1 - Elevation - RCC work Completed 98%.

March 2026

Tower 1: - Elevation

December 2025

Tower 1 : Pargonala, LMR, OHWT 60% Completed

1st November to 15th November 2025

Tower 1 - RCC work Terrace slab (36th slab) Casting work 100% completed

15th october to 31st October 2025

Tower 1 : Terrace floor (36th slab) shuttering and reinforcement work completed 90%.

1st october to 15 October 2025

Tower 1 - Terrace floor (36th slab) shuttering and reinforcement work completed 60%

Construction Update September 2025

Tower 1 - 35th slab shuttering and reinforcement work completed 40%

Construction Update August 2025

Tower 1 - 33rd shuttering work and reinforcement work completed 50%

Construction Update July 2025

Tower 1 :- 27th slab shuttering work and reinforcement work completed 10%.

Construction Update May 2025

Tower 1 :- Elevation - 23rd slab - 100% completed

Construction Update April 2025

Tower 1 :- Elevation – 21st Slab Completed 100%

Construction Update March 2025

Tower-1:- 18th ( Typical 13th) slab 100 % completed. 19th ( Typical 14th) part 1 shuttering and reinforcement t work in progress (completed 55 %).

Construction Update Jan 2025

Tower-1:- 16 slab -100% completed. For 17th slab -shuttering and reinforcement work in progress (completed 50%).

Construction Update Dec 2024

Tower-1:- 14 slab -100% completed. For 15th slab -shuttering and reinforcement work in progress(completed 50%).

Construction Update Nov 2024

Tower-1:- 4th Typical floor - 11th slab Casting 100% completed.

Construction Update Oct 2024

Construction Update Sept 2023

Construction Update June 2023

Construction Update April 2023